access icon free Availability analysis of power substation automation architectures with PRP and HSR protocols

Industrial automation has been widely used in electric power substations. In this context, the IEC 61850 standard provides for the utilisation of redundancy in the data link layer to increase frame reception probability. This study aims to evaluate the availability of two power substation automation architectures based on the IEC 62439-3 standard, which describes two redundancy protocols named parallel redundancy protocol (PRP) and high-availability seamless redundancy (HSR). The authors evaluate both architectures using either PRP or HSR protocol against using no redundancy protocols. The reliability block diagram method has been used, and afterwards, the mean time to failure and availability have been calculated. Results show that the utilisation of redundancy protocols allied to the repair during the mission allows classifying the architectures in the higher availability class according to CEI IEC 870-4.

Inspec keywords: substation automation; substation protection; local area networks; substations; telecommunication network reliability; protocols; redundancy; IEC standards

Other keywords: parallel redundancy protocol; redundancy protocols; HSR; higher availability class; frame reception probability; electric power substations; industrial automation; IEC 62439-3 standard; PRP; availability analysis; IEC 61850 standard; power substation automation architectures; high-availability

Subjects: Reliability; Protocols; Substations; Power engineering computing; Computer communications

References

    1. 1)
      • 8. CEI IEC 870-4: ‘Telecontrol equipment and systems – part 4: performance requirements’, 1990.
    2. 2)
      • 6. Tournier, J.-C., Werner, T.: ‘A quantitative evaluation of IEC 61850 process bus architectures’. Proc. IEEE PES General Meeting, Minneapolis, USA, July 2010, pp. 18.
    3. 3)
      • 15. Jain, R.: ‘The art of computer systems performance analysis: techniques for experimental design, measurement, simulation, and modeling’ (Wiley, New York, USA, 1991, 1st edn.).
    4. 4)
      • 3. IEC 61850-8-1: ‘Communication network and systems for power utility automation – part 8-1: specific communication service mapping (SCSM) – mappings to MMS (ISO 9506-1 and ISO 9506-2) and to ISO/IEC 8802-3’, 2011.
    5. 5)
      • 2. Zadeh, M.R.D., Sidhu, T.S., Klimek, A.: ‘Suitability analysis of practical directional algorithms for use in directional comparison bus protection based on IEC61850 process bus’, IET Gener. Transm. Distrib., 2011, 5, (2), pp. 199208.
    6. 6)
      • 12. Rausand, M., Hoyland, A.: ‘System reliability theory: models, statistical methods, and applications’ (Wiley, Hoboken, NJ, USA, 2004, 2nd edn.).
    7. 7)
      • 11. Araujo, J., Lázaro, J., Astarloa, A., et al: ‘High availability automation networks: PRP and HSR ring implementations’. Proc. IEEE Int. Symp. Industrial Electronics, Hangzhou, China, May 2012, pp. 11971202.
    8. 8)
      • 5. Hajian-Hoseinabadi, H.: ‘Availability comparison of various power substation automation architectures’, IEEE Trans. Power Deliv., 2013, 28, (2), pp. 566574.
    9. 9)
      • 13. Billinton, R., Allan, R.N.: ‘Reliability evaluation of engineering systems: concepts and techniques’ (Plenum, New York, USA, 1992, 2nd edn.).
    10. 10)
      • 9. Kumar, S., Das, N., Islam, S.: ‘High performance communication redundancy in a digital substation based on IEC 62439-3 with a station bus configuration’. Proc. Australasian Universities Power Engineering Conf., Wollongong, Australia, September 2015, pp. 15.
    11. 11)
      • 14. IEEE 801.D: ‘IEEE standard for local and metropolitan area networks: media access control (MAC) bridges’, 2004.
    12. 12)
      • 10. Goraj, M., Harada, R.: ‘Migration paths for IEC 61850 substation communication networks towards superb redundancy based on hybrid PRP and HSR topologies’. Proc. IET Int. Conf. on Developments in Power Systems Protection, Birmingham, UK, April 2012.
    13. 13)
      • 4. IEC 62439-3: ‘Industrial communication networks – high availability automation networks – part 3: parallel redundancy protocol (PRP) and high-availability seamless redundancy (HSR)’, 2016.
    14. 14)
      • 16. U. S. Military Standard 785B: ‘Reliability program for systems and equipment development and production’, 1980.
    15. 15)
      • 1. IEC 61850: ‘Communication networks and systems for power utility automation’, 2018.
    16. 16)
      • 7. Sivanthi, T., Görlitz, O.: ‘A systematic approach for calculating reliability of substation automation systems functions’. Proc. IEEE Int. Energy Conf. and Exhibition, Florence, Italy, September 2012, pp. 957962.
http://iet.metastore.ingenta.com/content/journals/10.1049/iet-gtd.2018.6364
Loading

Related content

content/journals/10.1049/iet-gtd.2018.6364
pub_keyword,iet_inspecKeyword,pub_concept
6
6
Loading