The term `project stage by stage' refers to the stage-by-stage high-level sequence of work activities relevant to the site installation and commissioning of HV equipment, specifically including the status of the equipment with reference to the power network company safety rules. Figure 24.1 illustrates the interaction between a project stage-by-stage document and the key scheme/project stages as shown in Figure 1.4. During the scheme development stage, an outline stage-by-stage document would usually be prepared to determine the optimum sequence of work stages by which the equipment is to be installed and commissioned. Following contract release, the project stage-by-stage document would be prepared in detail and subsequently implemented during site installation and commissioning.